North West programme of urgent repairs – progress updates14 Feb 2018

BEAR Scotland teams are working to carry out a £4M programme of urgent repairs across the North West trunk road network.

See below for an update on the works programme.

Click here to read about progress on the A83 urgent repair programme of surfacing works.  

For real time journey information, please visit Traffic Scotland at www.trafficscotland.org, twitter @TrafficScotland or via their new mobile site, my.trafficscotland.org.

 

Thursday 17 May

 

A87 Cluanie

Today teams finished surfacing operations after laying a total of 240 tonnes of new road material.

A887 Invermoriston

Teams have made great progress by milling out over 825 tonnes of road surface in preparation for surfacing.

 

Wednesday 16 May

 

A835 South of Garve

Operations have returned to the site at Killin Farm, laying 220 tonnes of new material across five patches.

A87 Cluanie

Works have restarted again today following mechanical issues apparent at the quarry. The team have been able to lay 160 tonnes of new material.

 

Tuesday 15 May

 

A835 Glascarnoch

Operations have continued to remove and install material across multiple patches resulting in 75 tonnes being replaced.

A87 Cluanie

Works have been delayed today with mechanical issues apparent at the quarry. Works due to continue tomorrow subject to the condition of the quarry.

 

Monday 14 May

 

A835 Glascarnoch

Operations have continued to remove and install material across multiple patches resulting in 75 tonnes being replaced.

A87 Cluanie

Surfacing works has continued today with the team laying 160 tonnes of new material.

 

Friday 11 May 

 

A835 Glascarnoch

Operations have continued surfacing across multiple patches of the site laying over 85 tonnes of new road surface. 

A87 Cluanie

Surfacing works have continued today with 160 tonnes of new material being laid in total.                                     

 

Thursday 10 May 

 

A835 Glascarnoch

Operations have continued surfacing across multiple patches of the site laying 80 tonnes. Further surfacing works to take place tomorrow. 

A87 Cluanie

Planing works continued today with the team removing 285 tonnes of road material. Surfacing works to take place tomorrow. 

 

Wednesday 9 May

 

A835 Glascarnoch

Operations have made good progress today laying 90 tonnes of new material.

A87 Cluanie

Operations have successfully laid 220 tonnes of new material. Operations are set to remove more material tomorrow.

 

Tuesday 8 May

 

A835 Glascarnoch

Operations have continued surfacing across multiple patches of the site laying over 130 tonnes of material.

A87 Cluanie

Surfacing works has continued today with the team laying 224 tonnes of new material.

 

Friday 4 May

 

A835 Glascarnoch

Operations have continued surfacing across multiple patches of the site. Surfacing to resume on Tuesday.

A87 Cluanie

The team have made excellent progress today with operations seeing 220 tonnes laid. Surfacing to resume on Tuesday.

 

Thursday 3 May

 

A835 Glascarnoch

The operations team have been experiencing mechanical issues today however have managed to install 62 tonnes of new material.

A87 Cluanie

The team have made further good progress today with operations seeing 880 tonnes of material removed from site.

 

Wednesday 2 May

 

A835 Loch Glascarnoch

Operations have removed and replaced 75 tonnes of material across multiple locations. Surfacing is to continue tomorrow.

A87 Cluanie

The team has successfully laid 200 tonnes of material today. The team intend to begin removing more material from site tomorrow.

 

Tuesday 1 May

 

A835 Glascarnoch

Works progressing well today with approximately 80 tonnes of old material removed and 80 tonnes of new material laid.

A87 Cluanie

The team were able to lay 220 tonnes of new material today.

 

Monday 30 April

 

A835 Glascarnoch

Due to a mechanical issue with our contractor’s plant, works at Glascarnoch did not resume today. Works is now set to get underway from tomorrow.

A87 Cluanie

Works progressing well today with the team laying 350 tonnes of material.

 

Friday 27 April

 

A835 South of Garve

Works to resume on Monday.

A85 Rob Roy’s Dip

Surfacing has been completed today with a total of an estimated 950 tonnes of material installed across the site.

A87 Cluanie

Works progressed well today with the team expected to remove 195 tonnes of old material from site. Works to continue on Monday.

 

Thursday 26 April

 

A85 Rob Roy’s Dip

Today the team have installed 200 tonnes of new material. Surfacing is programmed for completion tomorrow.

A87 Cluanie

Works are progressing well today with 175 tonnes of new material laid.

A828 Culcharan Farm

Operations have completed required resurfacing on site today removing and installing 160 tonnes of material.

A835 Loch Glascarnoch

Works progressed well today with 120 tonnes of new material installed. The project is  to resume on Monday.

 

Wednesday 25 April

 

A835 South of Garve

Operations were able to lay 90 tonnes of material before a mechanical malfunction was encountered at the quarry. Works are to resume tomorrow.

A85 Rob Roy’s Dip

The team was able to remove 400 tonnes of old road material and install 240 tonnes of new surface material.

A87 Cluanie

Operations have laid 250 tonnes of material today. Unfortunately the surface course was unable to be completed today so traffic lights will be left running over night for safety of road users.

 

Tuesday 24 April

 

A835 South of Garve

Operations have started work on the first of three with the team removing and installing 72 tonnes of road surface material.

A85 Rob Roy’s Dip

The team was able to remove 400 tonnes of old material and install 240 tonnes of new surface.

A87 Cluanie

Operations have progressed well today with the team laying 306 tonnes of surface course.

 

Monday 23 April

 

A82 North of Inverherive

Surfacing operations were completed on Saturday with over 1,000 tonnes of new material installed at the A82 North of Inverherive.

A835 Inchbae

Operations have completed surfacing today with a final total of 2,017 tonnes of new material installed. The team will now move on to the A835 South of Garve Site from tomorrow.

A85 Rob Roy’s Dip

Today teams have started removing material from site.

A87 Cluanie

Operations started work today by removing 900 tonnes of old material from site.

 

Friday 20 April

 

A82 North of Inverherive

A further 290 tonnes of new material has been laid at the A82 North of Inverherive site today. Surfacing is planned to be completed tomorrow.

A835 Inchbae

Operations have removed 285 tonnes of material today. Surfacing works is expected to be completed on Monday.

A85 Rob Roy’s Dip

Works is programmed to get underway on Monday.

A87 Cluanie

Works is programmed to begin on Monday.  Read more about this project here.

A835 Loch Glascarnoch

Works is programmed to start on Monday.

 

Thursday 19 April

 

A82 North of Inverherive

The team have made good progress today with just over 200 tonnes of new material laid at the A82 North of Inverherive site. A further two days of surfacing are planned with works being completed on Saturday 21 April.

A85 West of Inveraray Junction

Works were completed last night with a total of 660 tonnes new material being laid over the course of the scheme. 

A835 Inchbae

Surfacing works were undertaken today with 390 tonnes of new material laid. Tomorrow it is expected that 285 tonne of material will be removed ahead of surfacing operations. 

 

 

Wednesday 18 April

 

A85 West of Inveraray 

Operations have removed 90 tonnes of old material and installed 140 tonnes of new material.

A82 North of Inverherive 

Operations have laid 200 tonnes of surface course.

A835 Inchbae

Today teams have laid 300 tonnes of surface course.

 

Tuesday 17 April

 

A82 An Torr

Works have been postponed tomorrow. New programme dates to be released once available.

A82 North of Inverherive

The team have made good progress today with milling operations completed on the A82 North of Inverherive site. Surfacing operations will get underway from tomorrow morning.

A85 West of Inveraray Junction

Works are progressing well with a further 230 tonnes of old material removed and 189 tonnes of new material installed. Works are to continue tonight.

A87 North of Kinlochourn Junction

Works have been postponed today. New programme dates to be released in due course.

A835 Inchbae

Works have recommenced today with the team removing 700 tonnes of material from the site.

 

Monday 16 April

 

A82 North of Ivverherive

Works on the A82 North of Inverherive site have started today with the team removing 380 tonnes of old material and installing 90 tonnes of new road material.

A85 West of Inveraray Junction

The team began surfacing works last night removing 270 tonnes of old material and installing 260 tonnes on new material. 

A87 Bee Haven

Works have been postponed today. New programme dates to be released as soon as they are available

A87 North of Kinlochourn Junction

Works to commence tomorrow.

A835 Inchbae

Works to continue tomorrow.

 

Friday 13 April

 

A82 South of Inverherive

Operations have completed surfacing works on the A82 South of Inverherive laying of 200 tonnes of material. Works will move to the A82 North of Inverherive site on Monday.

A85 West of Inveraray Junction

Works start on Sunday under an overnight road closure for safety, 9pm to 7am. 

A87 Bee Haven

Works will begin on Monday.

A835 Inchbae

Teams will start work on Monday.

 

Thursday 12 April

 

A85 Crianlarich

Surfacing on the A85 at Crianlarich was completed this morning, with 100 tonnes of new road surface materials installed.

A82 South of Inverherive

Teams have started to remove the worn out road surface material ready for the start of surfacing operations tomorrow (Friday). 

 

Wednesday 11 April

 

A85 Crianlarich Area

Operations have removed and replaced 80 tonnes of material. Surfacing at the A85 site is due for completion tomorrow. Work will then begin on the A82 South of Inverherive site.

 

Tuesday 10 April

 

A85 Crianlarich 

Another 80 tonnes of new road material was laid today.  Surfacing works are set to continue tomorrow.

 

Monday 9 April

 

A85 Crianlarich 

80 tonnes of material was laid today. Works will continue tomorrow.

 

Tuesday 3 April

No further work planned this week.  Operations will resume Monday 9 April.

 

Monday 2 April

 

A9 Banniskirk

Operations completed today with a total of 1,222 tonnes of new material laid.

 

Friday 30 March

 

A9 Banniskirk

Works have been delayed today due to the heavy rainfall in the area. Works programmed to resume tomorrow. Surfacing due for completion on Monday. 

A835 Inchbae

Operations have completed works today with a total of 1,953 tonnes of material replaced on the site.

 

Thursday 29 March

 

A9 Banniskirk

Operations have commenced surfacing today laying 400 tonnes of material.

A835 Inchbae

Work has progressed well today with 360 tonnes of new material installed.

A85 Taynuilt

Operations have completed works today with a total of 230 tonnes of material replaced on the site.

 

Wednesday 28 March

 

A9 North of Trinafour, southbound

Work was completed today with a total of 2629 tonnes of material installed.

A9 Banniskirk

Operations have progressed well today with 600 tonnes of material removed.

A828 Creagan Sea Wall

Surfacing was completed today with a total of 416 tonnes of material installed.

A835 Inchbae

Surfacing started today with 340 tonnes of new material installed.

A85 Taynuilt

Works is programmed to begin tomorrow.

 

Tuesday 27 March

 

A9 North of Trinafour, southbound

Operations have successfully laid 380 tonnes of new material today.

A9 Banniskirk

Works commenced today with operations removing 600 tonnes of old material.

A828 Creagan Sea Wall

Adverse weather conditions have delayed work today with operations able to removed 100 tonnes of material. Works is due to be completed tomorrow.

A835 Inchbae

Works has progressed well today removing 500 tonnes of material and laying 50 tonnes of new material.

A85 Taynuilt

Works is programmed to start on Thursday.

 

 

Monday 26 March

 

A9 Borgue

Work was completed today with a total of 1093 tonnes of new material installed.

A9 North of Trinafour, southbound

Operations have laid 380 tonnes of new material today.

A9 Banniskirk

Works is programmed to start tomorrow.

A828 Creagan Sea Wall

Operations have strated work today with 160 tonnes of material removed allowing the team to install a ‘Geogrid’ membrane before laying 146 tonnes of new material.

A835 Inchbae

Works started today with operations removing more than 850 tonnes of material.

 

Friday 23 March

 

A9 Borgue

Works was cancelled today due to heavy rainfall and fog. Work is due for completion tomorrow.

A9 North of Trinafour SB

Operations were able to complete the ‘crack and seat’ process in preparation for laying material. Works to continue tomorrow.

A82 Glen Gloy

Work was completed last night laying a total of 200 tonnes of new material.

A82 South of Invermoriston

Work was completed today laying a total of 215 tonnes of new material.

A9 Banniskirk

Works is programmed to commence on Monday.

A828 Creagan Sea Wall

Works is programmed to commence on Monday.

A835 Inchbae

Works is programmed to commence on Monday.

 

Thursday 22 March

 

A9 Borgue

Works progressing well today with operations laying 240 tonnes of new material.

A9 North of Trinafour, southbound

Works progressing well with 730 tonnes of material removed from site today.

A82 Glen Gloy

Surfacing is programmed for completion tonight between 7pm and 7am.

A87 Hinnisdale

Resurfacing was completed today with operations laying a total of 585 tonnes of new material.

A830 West of Glenfinnan

Work was cancelled last night due to heavy rainfall. New programmed dates will be released in due course.

A82 South of Invermoriston

Operations started today with teams removing 200 tonnes of material and installing 90 tonnes of new material. Works to continue tomorrow.

 

Wednesday 21 March

 

A9 Borgue

Works progressed well today with operations removing 407 tonnes of material and laying 206 tonnes of new material.

A9 North of Trinafour, southbound

Works progressing well with 230 tonnes of new material laid today and 630 tonnes of material removed.

A82 Alltsigh

Works have been completed today with a total of 612 tonnes of new material laid.

A82 Glen Gloy

Works are programmed for completion on Thursday between 7pm and 7am.

A87 Hinnisdale

Works recommenced today and removed 320 tonnes of material and installed 160 tonnes of new material. Work is programmed for completion tomorrow.

A830 West of Glenfinnan

Work commenced last night under night time road closure. Operations made good progress removing and replacing 166 tonnes of material.

A82 South of Invermoriston

Works is programmed to start tomorrow.

 

Tuesday 20 March

 

A9 Borgue

Works progressed well today with operations removing and replacing 160 tonnes of material.

A9 North of Trinafour, southbound

Works progressing well with 580 tonnes of material laid today.

A82 Alltsigh

Works are scheduled to recommence tomorrow.

A82 Glen Gloy

Works are programmed for completion on Thursday between 7pm and 7am.

A87 Hinnisdale

Work is programmed to resume tomorrow.

A87 Borve Jct

Work was completed today with a total of 130 tonnes of new material installed. This included resurfacing on the A850, on behalf of The Highland Council.

A830 Loch Eilt

Work was completed last night with a total of 438 tonnes of new material installed.

A830 West of Glenfinnan

Work is programmed to commence tonight under night time road closure.

 

Monday 19 March

 

A9 Borgue

Operations have removed 445 tonnes of defective surface course today.

A9 North of Trinafour, southbound

Surfacing operations began today with 120 tonnes of material laid.

A82 Alltsigh

Surfacing resumed today, with 260 tonnes of material being laid. Works are scheduled to recommence Wednesday 21 March.

A82 An Torr

Unfortunately, operations at this site have been postponed. New programmed dates will be released in due course.

A87 Hinnisdale

Work was postponed today to allow a higher priority schemes to take place. Work is programmed to resume on Wednesday.

A87 Borve Jct

120 tonnes of defective surface course was removed today.

A830 Loch Eilt

Works are scheduled to resume tonight, between the hours of 7pm and 7am under a full road closure.

 

Friday 16 March

 

A9 Dunbeath

Work was completed today with a total of 180 tonnes of new material installed. 

A82 Alltsigh

Works have progressed well with 135 tonnes of new material laid today. Works to resume on Monday.

A82 Glen Gloy

Operations have seen 81 tonnes of new material installed. Work is programmed to continue on Saturday.

A85 Crianlarich

Due to the forecasted inclement weather, work is programmed to resume on Wednesday.

A87 Hinnisdale

Work progressing well with 120 tonnes of material laid today. Operations are scheduled to resume on Monday.

A9 Borgue

Work is programmed to commence on Saturday. 

A9 North of Trinafour, southbound

Work is programmed to commence on Saturday.

A830 Loch Eilt Bridge

Works is programmed to commence on Sunday under night time road closure. 

 

Thursday 15 March

 

A9 Dunbeath

Works have commenced today with 180 tonnes of material removed from site. Surfacing to begin tomorrow.

A9 Drumochter (Wade Stone)

Works were completed today with a total of 3,298 tonnes of new material installed.

A82 Altsigh

Works have started today with 516 tonnes of material removed and 45 tonnes of material laid.

A82 Glen Gloy

Works have commenced today with 190 tonnes of material removed and replaced on site.

A85 Crianlarich

Works have commenced today with 260 tonnes of material removed with 20 tonnes of material installed. Due to the forecasted inclement weather, work is programmed to resume on Wednesday.

A87 Hinnisdale

Works have commenced today with 275 tonnes of material removed with 160 tonnes of material installed.

 

Wednesday 14 March

 

A9 Spittal to Georgemas

Works was completed today with a total of 3,792 tonnes of new road material installed.

A9 Drumochter (Wade Stone)

Works progressing well with 444 tonnes of new material laid today.

A82 Ardlui to Falls of Falloch

Works completed today with a total of 1,159 tonnes of new material installed.

A87 Druim nan Cleochd

Project completed today with a total of 1, 083 tonnes of new material installed.

A82 North of Spean Bridge

Works completed today with a total of 157 tonnes of new material installed.

A84 Kilmahog

Works were finished today with a total of 293 tonnes of new material installed.

A82 Altsigh

Due to a mechanical issue with our contractor’s plant, works on Altsigh did not commence today. Works is now due to commence tomorrow.

 

Tuesday 13 March

 

A9 Spittal to Georgemas

Operations have seen a further 240 tonnes of new material laid today. Works to continue tomorrow.

A887 West of Achlain

Work was completed today with a total of 2,168 tonnes of new material installed.

A9 Drumochter (Wade Stone)

Works progressing well with 440 tonnes of new material laid today.

A82 Ardlui to Falls of Falloch

Works progressing well with 185 tonnes of new material installed today.

A87 Druim nan Cleochd

Operations have seen a further 220 tonnes of new material laid today.

A82 North of Spean Bridge

A total of 72 tonnes of material has been removed with 56 tonnes of material installed. Works to continue tomorrow.

A84 Kilmahog

Works have commenced today with 306 tonnes of material removed and 183 tonnes of material installed, work continues tomorrow. 

 

Monday 12 March

 

A9 Spittal to Georgemas

Operations have seen a further 300 tonnes of new material laid today. 

A887 West of Achlain

Work progressing well with a further 290 tonnes of new material laid today. 

A9 Drumochter (Wade Stone)

Operations have commenced laying new material today, with 390 tonnes successfully installed.

A82 Ardlui to Falls of Falloch

A total of 80 tonnes of material has been removed and replaced on site today.

A87 Druim nan Cleochd

Work progressing well with 320 tonnes of new material laid today. 

A84/A85 Lochearnhead

Work was completed today with a total of 630 tonnes of new material installed across the two sites.

A86 West of Roybridge

Work was completed today with a total of 130 tonnes of new material installed.

A82 North of Spean Bridge

Work will commence tomorrow for one day.

 

Friday 9 March

 

A9 Spittal to Georgemas

Operations have laid 300 tonnes of new material today. Work to resume on Monday.

A887 West of Achlain

120 tonnes of new material has been laid. Works will continue on Saturday.

A9 Drumochter (Wade Stone)

Operations have removed 570 tonnes of material today. Work will begin to lay the new material on Monday.

A82 Fort William to Torlundy

Work completed today.

A82 Ardlui to Falls of Falloch

A total of 185 tonnes of material has been removed today.

A87 Druim nan Cleochd

320 tonnes of new material has been laid today. 

A84/A85 Lochearnhead

The A85 section of the site has been completed today with 95t of new material laid. Works will continue through the weekend.

A86 West of Roybridge

Work will commence on Monday.

 

Thursday 8 March

 

A9 Spittal to Georgemas

280 tonnes of surface course has been laid. Works continues tomorrow.

A887 West of Achlain

Works has progressed well today with 300 tonnes of material laid.

A9 Drumochter (Wade Stone)

Works has progressed well with 530 tonne of material laid and a further 650 tonnes of material removed.

A82 Fort William to Torlundy

Operations were able to lay 240 tonnes of new material today.

A82 Ardlui to Falls of Falloch

A total of 170 tonnes of new material has been laid today.

A87 Druim nan Cleochd

180 tonnes of new material has been laid today. Works will continue at the Drium nan Cleochd site tomorrow.

A84/A85 Lochearnhead

Operations commenced today at the Lochearnhead site with 116 tonnes of material removed and 61 tonnes of material laid.

 

Wednesday 7 March

 

A9 Spittal to Georgemas

Work progressed well with 170 tonnes of new material laid today. Work continues tomorrow.

A887 West of Achlain

Work progressed well with 214 tonnes of surface course laid today.

A9 Drumochter (Wade Stone)

Work progressed well with more than 350 tonnes of new material laid.

A82 Fort William to Torlundy

Operations have laid 230 tonnes of surface course today.

A82 Ardlui to Falls of Falloch

Operations progressed well today with 230 tonnes of material removed and 200 tonnes of new material laid.

A87 Druim na Cleochd

Work recommences on Friday.

A87 Head of Loch Ainort

Work completed today. A total of 400 tonnes of new material has been laid.

A87 North of Broadford

Work is programmed to commence tomorrow for one day.

A85 St Fillans

Work completed today. A total of 150 tonnes of new material has been laid.

A84/A85 Lochearnhead

Work will commence tomorrow for five days. Motorists are advised that work will continue over the weekend on both Saturday and Sunday.

 

Tuesday 6 March

 

A9 Spittal to Georgemas

Operations have been able to lay 360 tonnes of binder material.

A887 West of Achlain

Work is due to recommence tomorrow.

A9 Drumochter (Wade Stone)

Operations were able to lay 312 tonnes of road material.

A82 Fort William to Torlundy

Operations have completed the Torlundy site today. Operations will move to the golf course site tomorrow.

A82 Ardlui to Falls of Falloch

Today’s work has seen operations mill 200 tonnes of material and lay 20 tonnes of binder. 

A87 Druim na Cleochd

Work recommences on Friday.

A87 Head of Loch Ainort

Today’s work has seen operations remove 393 tonnes of material and  lay 45 tonnes of binder course.

A87 North of Broadford

Work is programmed to start on Thursday for one day.

A85 St Fillans

Milling operations removed 161 tonnes of material from site.  Tomorrow will see 130 tonnes of surface course laid. 

 

Monday 5 March

 

A9 Spittal to Georgemas

Milling operations resumed today with 500 tonnes of material removed from site.

A887 West of Achlain

Work has been cancelled today and tomorrow due to inclement weather. Forecasts will be reviewed and updates issued, should work be feasible on Wednesday.

A9 Drumochter (Wade Stone)

Work was cancelled today due to inclement weather. Work will recommence tomorrow.

A82 Fort William to Torlundy

Works resumed today seeing surface course laid across 300m at 100mm through the site. 100m and the bus bay remaining for the Torlundy site.

A82 Ardlui to Falls of Falloch

Work progressed well today with 40 tonnes of new material laid at Inverarnan.

A87 Druim na Cleochd

Work was cancelled today due to forecasted inclement weather. Work recommences on Friday.

A87 Head of Loch Ainort

Work is programmed to commence tomorrow for two days.

A87 North of Broadford

Work is programmed to start on Thursday for one day.

A85 St Fillans

Work was cancelled today due to forecasted inclement weather. Work is now scheduled to commence tomorrow.

 

Wednesday 28 February

 

A9 Spittal to Georgemas

Following an onsite inspection this morning, work was cancelled. Work is also cancelled tomorrow due to forecasted inclement weather. Forecasts will be reviewed and updates issued, should work be feasible on Friday.

A887 West of Achlain

Today saw good progress on site with further deteriorated sections removed, in preparation for resurfacing. Works are programmed to continue tomorrow.

A9 Drumochter (Wade Stone)

Operations have been postponed for the remainder of the week, due to forecasted inclement weather.

A82 Fort William to Torlundy

Following an onsite inspection this morning, work was cancelled. An inspection will be carried out tomorrow to decide if work can progress.

A82 Ardlui to Falls of Falloch

Following an onsite inspection this morning, work has been postponed today. Work has been cancelled for the remainder of this week due to the forecasted inclement weather. Operations will recommence Monday morning at Inverarnan.

A87 Druim na Cleochd

Following an onsite inspection this morning, work was cancelled. Work is also cancelled tomorrow due to forecasted inclement weather. Forecasts will be reviewed and updates issued, should work be feasible on Friday.

 

Tuesday 27 February

 

A9 Spittal to Georgemas

Good progress today with a further 440 tonnes of material removed from the site. Work is programmed to continue tomorrow, subject to an onsite inspection tomorrow morning.

A887 West of Achlain

Today’s work saw 160 tonnes of new material laid. Work is programmed to continue on site tomorrow.

A9 Drumochter (Wade Stone)

Today’s milling operations have seen around 800 tonnes of material removed from the site. Tomorrow and Thursday’s operations have been postponed due to forecasted inclement weather.

A82 Fort William to Torlundy

Work commenced on site today with 277 tonnes of material removed and 34 tonnes of new material laid. Work continues tomorrow under the same traffic management system. Motorists are advised to expect delays.

A82 Ardlui to Falls of Falloch

Work commenced on site today with 170 tonnes of material removed and 170 tonnes of new material laid. Work will continue at Inverarnan tomorrow, subject to an onsite inspection tomorrow morning

A87 Druim na Cleochd

A total of 470 tonnes of material has been removed today. With a further 470 tonnes expected to be removed tomorrow. Tomorrow’s work on site has been postponed due to forecasted inclement weather.

 

Monday 26 February

 

A9 Spittal to Georgemas

Good progress today with a further 500 tonnes of material removed from the site.

A887 West of Achlain

Today’s work saw 300 tonnes of new material laid. 

A9 Drumochter (Wade Stone)

Today’s milling operations have seen 413 tonnes of material removed from the site. 

A82 Fort William to Torlundy

Work commenced on site today with 277 tonnes of material removed and 34 tonnes of new material laid. Work continues tomorrow under the same traffic management system. 

A82 Ardlui to Falls of Falloch

Work commenced on site today with 165 tonnes of material removed and 165 tonnes of new material laid. Work will continue at the Falls of Falloch site tomorrow.

A87 Druim na Cleochd

A total of 580 tonnes of material has been removed today. With a further 470 tonnes expected to be removed tomorrow. 

 

Friday 23 February

 

A9 Spittal to Georgemas

Milling operations have seen a further 500 tonnes of material removed from the site. Works will continue tomorrow.

A887 West of Achlain

Work progressing well with 230 tonnes of new material laid today. Resurfacing work is due to continue Monday.

A9 Drumochter (Wade Stone)

Work starts on Monday morning at 7am. Operations will be carried out under a convoy traffic management system.

A82 Fort William to Torlundy

Work will recommence on Monday at 7am between Carrs Corner and Torlundy. Operations will be carried out under a convoy traffic management system for safety.

A82 Ardlui to Falls of Falloch

Work commences Monday morning at 7am. Operations will be carried out under a convoy traffic management system.

A87 Druim na Cleochd

Work commences Monday morning at 7am. Operations will be carried out under a convoy traffic management system.

 

Thursday 22 February

 

A9 Spittal to Georgemas

Approximately 440 tonnes of new material has been laid across both lanes today.

A82 Fort William to Torlundy

Resurfacing works at the Morbaine site were completed last night.

A830 Criche Bridge

Resurfacing works completed today.

A887 West of Achlain

155 tonnes of new material was laid today.

 

Wednesday 21 February

 

A9 Spittal to Georgemas

Today’s work involved removal of approximately of 500 tonnes of material. 

A82 Fort William to Torlundy

Works resumed last night and saw 197 tonnes of new material laid at the Morbaine site. Operations switched to Nevis Bridge at midnight with resurfacing completed by 3:15am. Operations will continue at the Morbaine site this evening with convoy working in place from 7pm – 7am.

A84 South of Strathyre

Resurfacing works completed today.

A830 Criche Bridge

Works progressed well today as 148 tonnes of new material laid. 

A887 West of Achlain

Today has seen a total of 230 tonnes of surface course being laid.

 

Tuesday 20 February

 

A9 Spittal to Georgemas

Works continued to make good progress as binder has been laid across the 500m across both lanes of the carriageway with an estimated 400 tonnes of material laid.

A82 Fort William to Torlundy

Due to a mechanical issue with our contractor’s plant, resurfacing works on Nevis Bridge were not completed last night. Work is programmed for completion overnight tonight. Unfortunately this will require a road closure for part of the night in order to facilitate. To reduce the impact on motorists, working hours have been reduced to 10pm – 2am. Hourly amnesties will remain in operation to allow traffic to flush as frequently as possible. The subsequent work phases remain unchanged and will be carried out as planned.

A84 South of Strathyre

The works have progressed well with 260 tonnes of material removed and 168 tonnes of new material laid.

A830 Criche Bridge

Works have started with the first layer of the new material laid today.

A887 West of Achlain

Work has progressed well today with 180 tonnes of new material being laid.

 

Monday 19 February

 

A9 Spittal to Georgemas 

Works commenced on site today with 500m of road surface removed in preparation for surfacing tomorrow.

A82 Fort William to Torlundy

Due to adverse weather, resurfacing works on Nevis Bridge were not completed last night. Work is programmed for completion overnight tonight. Unfortunately this will require a road closure for part of the night in order to facilitate. To reduce the impact on motorists, working hours have been reduced to 10pm – 2am. Hourly amnesties will remain in operation to allow traffic to flush as frequently as possible. The subsequent work phases remain unchanged and will be carried out as planned.

A84 South of Strathyre

Resurfacing works have progressed well today, with teams on programme.

A887 West of Achlain

Work progressed well today with 250 tonnes of new material installed.

A889 Cathar Mor

Resurfacing operations were completed today.

Other Routes Overall

Members of the public are reminded that planing operations have been undertaken at the above sites. Motorists will be running on a temporary surface until resurfacing operations can be completed and are advised to drive with care and adhere to the 30mph temporary speed restriction.

 

Friday 16 February


A84 South of Strathyre

Resurfacing works have progressed well today, with 160tonnes of new surfacing material laid. Works will recommence on Monday 19 February.

A887 West of Achlain 

Unfortunately due to overnight snowfall, surfacing and milling operations were halted. Works are due to resume on Monday 19 February.

A889 Cathar Mor

Unfortunately due to forecasted inclement weather, surfacing operations will not be completed this week. Work will recommence for one day on Monday 19 February under a full road closure, 7am – 7pm.

Other Routes Overall

Members of the public are reminded that planing operations have been undertaken at West of Achlain, Cathar Mor and South of Strathyre. Motorists will be running on a temporary surface until resurfacing operations can be completed and are advised to drive with care and adhere to the 30mph temporary speed restriction.

 

Thursday 15 February

 

A84 South of Strathyre

Works have continued today and are expected to be completed by next Wednesday, weather permitting.  Planing works have been carried out, meaning motorists a running on a temporary road surface.  A reduced speed limit of 30mph is in place for safety until resurfacing is completed.  

A85 Connel Village

Final night of resurfacing was completed last night, application of white lines is expected to take place on Monday.  

A887 West of Achlain

Unfortunately works have been cancelled today and tomorrow due to overnight snowfall and inclement weather.  Planing works have been carried out, meaning motorists a running on a temporary road surface.  A reduced speed limit of 30mph is in place for safety until resurfacing is completed.  

A889 Cathar Mor

Unfortunately works were cancelled today (Thursday) and tomorrow (Friday) due to further adverse weather conditions. Resurfacing will hopefully be undertaken on Monday, weather permitting, under a full road closure for safety, 7am to 7pm.  Planing works have been carried out, meaning motorists a running on a temporary road surface.  A reduced speed limit of 30mph is in place for safety until resurfacing is completed.  

 

Wednesday 14 February

 

A84 South of Strathyre

Heavy rain prevented operations from continuing, work programmed to continue this week. 

A85 Connel Village

Nearly 200 tonnes of new road surface material was laid overnight, with works provisionally set to be completed tonight.  

A887 West of Achlain

Unfortunately surfacing and milling operations were halted due to the adverse weather conditions.

A889 Cathar Mor

Final section of resurfacing has been delayed due to weather conditions, set to be completed this week.  

downloadNew File