Works start Friday 10 September A section of the A9 near Dupplin Loch, south west of Perth, is to benefit from surfacing improvements worth £305,000 with works set to get underway this weekend. The improvements will address defects in the road surface on the southbound section of the A9 past Dupplin Loch, creating a … Continued
Works start Thursday 16 September over three nights A section of the A96 near Huntly is to benefit from surfacing improvements worth £145,000 with work set to get underway this week. The improvements will address defects across a 500m section of the A96 at Leys of Dummuies, east of Huntly, creating a safer and … Continued
Works start Monday 13 September for five days A section of the A95 south of Dalvey is to benefit from surfacing improvements worth £165,000 with work set to get underway next week. The improvements will address defects in the road surface on the A95, between Cromdale and Tormore creating a safer and smoother road surface … Continued
Works start Monday 13 September for five nights A section of the A90 northbound near Moncur is to benefit from surfacing improvements worth £320,000, with work set to get underway next week. The improvements will address defects in the road surface on the northbound section of the A90 between Inchture and Moncur, creating a safer … Continued
Kessock Bridge abseil team helps raise over £1,210 BEAR Scotland donates additional £1,000 Highland Hospice, the charity that helps people living with an advancing, life shortening illness in the Highlands to live the best possible life, as well as supporting their families and carers, has benefited from a £2,210 boost from BEAR Scotland. A five-strong … Continued
Next stage expected to take approximately nine months to complete The next stage of landslip mitigation measures at the Rest and Be Thankful got underway this week to help improve landslip resilience to the A83. The £3.5M project will see the construction of a further catch-pit next to the trunk road, and will be located … Continued
10 overnight road closures will commence Friday 10 September A section of the eastbound M8 after the junction 3 on-slip is set to benefit from resurfacing improvements worth £820,000. For the safety of workers and road users, the M8 will be closed in the eastbound direction between Junction 3a and Junction 2 from 20:30 until … Continued
Project to begin on Sunday 5 September for three weeks Overnight road closures in place for safety, 8pm to 6am, excluding Friday and Saturday nights Essential surfacing improvements at five locations on the A86 and A889 are set to get underway from Sunday. The programme of improvements will see over 2km of the A86 and … Continued
Friday 3 September OVERNIGHT CLOSURES REQUIRED FOR THE PLANNED SURFACING IMPROVEMENTS ON THE A92 BETWEEN FERNIE CASTLE AND AYTON Please be advised that surfacing improvements planned to take place this weekend on the A92 near Fernie in Fife have been extended. The weekend improvements are still going ahead as planned however overnight … Continued
£320,000 SURFACING IMPROVEMENTS Works start Monday 6 September over one week A section of the A96 near Huntly is to benefit from surfacing improvements worth £320,000 with work set to get underway from Monday 6 September. The improvements will address defects across a 650m section of the A96 at Newtongarry, creating a safer … Continued
Two-week programme of overnight lane closures begins 5 September 2021 Slip road closure during first week of works A two-week programme of overnight lane and slip road closures is set to begin on the southbound M876 on Sunday 5 September, to allow an £80,000 package of road safety improvements to be completed. Transport Scotland’s operating … Continued