Current forecast indicates heavy over night rain will clear later this morning. Further to this morning’s hillside inspection and updated forecast the A83 will therefore reopen to traffic at 11am. Further to this morning’s hillside inspection and updated forecast, traffic will move from the Old Military Road Local Diversion Route to the A83 … Continued
Updated forecast for today indicates an increase in predicted overnight rainfall and increase in hillside saturation levels. As a precaution, A83 traffic will therefore be diverted onto the Old Military Road from 7pm tonight. A83 will re-open to traffic on Thursday 2 February subject to outcomes of the morning inspection. Given updated forecast … Continued
The sequence of traffic signals at the junction will be amended on Sunday 5 February. The traffic lights will be turned off from 8am to 8.15am. Traffic will be managed by BEAR Scotland staff during this time. Safety improvements will be made by BEAR Scotland at the A82 Kenneth Street/Tomnhurich Street junction, Inverness, … Continued
Works planned for Tuesday 31 January will now begin on Tuesday 7 February. The project will take three nights to complete. A full road closure will be in place, with amnesties. Please be advised that overnight resurfacing works planned for the A835 Rogie to Tarvie, north of Contin, which were due to … Continued
Works will begin on Monday 6 February for two nights. A full road closure with signed diversion will be in place both nights. A drainage investigation project is set to start on the A85 West Connector on the outskirts of Perth (connecting to the junction with the B9993). The works will take place … Continued
Works start Sunday 5 February for two nights. Full road closure between 8pm and 6am. A831 traffic to be diverted. Amnesties will be in place on the A82. Overnight resurfacing works will be carried out at the A82 Drumnadrochit for two nights, beginning Sunday 5 February. The £40,000 investment by Transport … Continued
Works planned for Sunday 29 January will now begin on Tuesday 31 January. The project will take three nights to complete. A full road closure will be in place, with amnesties. Please be advised that overnight resurfacing works planned for the A835 Rogie to Tarvie, north of Contin, which were due to … Continued
Project 1 will now begin on Thursday 9 February for four nights. Project 2 to begin on Wednesday 15 February for six nights. Overnight road closures in place for safety, 8pm to 5am. Please be advised that essential surfacing improvements which were due to get underway at two locations on the A82, … Continued
The first phase was completed on Thursday 22 December. The second phase begins on Tuesday 31 January for seven nights. Overnight lane closures with convoy system in place for safety, 7pm to 5am. The first phase of an important road improvement project on the A83 south of Butterbridge was completed on 22 December … Continued
Project 1 to begin on Wednesday 8 February for four nights. Project 2 to begin on Tuesday 14 February for five nights. Overnight road closures in place for safety, 8pm to 5am. Essential surfacing improvements are set to get underway at two locations on the A82, between Tarbet and Crianlarich, on Wednesday … Continued
Due to weather conditions, the project due to begin today (Tuesday 17 January) has been postponed by one day. Weather permitting, works will take place on Wednesday 18 January. Day-time convoy works between 7am and 7pm. . Please be aware that essential surfacing improvements, planned to take place on the A82 North of Nevis … Continued
Traffic to operate on the A83 under traffic signal control today and overnight due to forecasts of dry weather and ground saturation levels reducing. Cold and dry conditions currently forecast for much of the coming week, which will allow saturation levels to reduce. Traffic at Rest and be Thankful will operate on the … Continued