October 15, 2020

A95 KEITH

£260,000 OVERNIGHT ROAD IMPROVEMENTS   A95 Approach to Haughs Bridge, Keith   Project starts Monday 19 October for seven nights   A section of the A95 near Haughs Bridge in Keith is set to benefit from resurfacing improvements worth £260,000 starting on Monday night. The improvements will involve teams addressing defects in the road surface … Continued

October 14, 2020

A92 LADYBANK

INNOVATIVE £925,000 SUSTAINABLE RESURFACING PROJECT TO TAKE PLACE ON A92 IN FIFE   Project involves recycling worn-out road materials for reuse in new road surface   Works start Friday 16 October for two weeks   Weekend road closures in place for safety     An innovative sustainable resurfacing project worth over £925,000 is set to … Continued

October 9, 2020

A90 BRECHIN TO BALNABREICH

£435,000 SURFACING IMPROVEMENTS   A90 Brechin to Balnabreich, southbound   Work starts Monday 12 October for ten nights A section of the A90 at Brechin is set to benefit from resurfacing improvements worth £435,000 with work set to get underway next week. The improvements will address defects in the road surface on the southbound section … Continued

October 6, 2020

A90 NORTH ELLON

£750,000 MAJOR CARRIAGEWAY IMPROVEMENTS A90 North of Ellon  Works Start Friday 23 October for eight days   A section of the A90 north of the North Ellon Roundabout is set to benefit from carriageway reconstruction improvements worth £750,000 starting later this month. The investment from Transport Scotland will see reconstruction improvements and carriageway strengthening works … Continued

October 6, 2020

A90 STIRLING VILLAGE

FIRST PHASE OF ROAD SAFETY IMPROVEMENTS ON A90 IN STIRLING VILLAGE UNDERWAY Work to continue for two weeks   A new road safety project on the A90 south of Peterhead is underway this week which will involve teams installing new electronic signs to help encourage road users to drive safely. The project will involve teams … Continued

October 6, 2020

M90 FRIARTON BRIDGE AND CRAIGEND INTERCHANGE

OVERNIGHT MAINTENACE UNDERWAY FOR M90 FRIARTON BRIDGE AND CRAIGEND INTERCHANGE   Routine bridge inspections and maintenance works for the M90 Friarton Bridge and M90 Junction 10 Craigend Interchange near Perth is underway this week.   The project will involve cleaning the bridge deck joints, channels and verges as well as drainage clearance and landscaping maintenance. … Continued

October 6, 2020

A90 STONEHAVEN

£800,000 SURFACING IMPROVEMENTS   A90 Stonehaven, southbound   Works start Wednesday 7 October for six days   A section of the A90 at Stonehaven is set to benefit from resurfacing improvements starting from tomorrow. The £800,000 improvements will address defects in the road surface on the southbound section of the A90 between the A957 Overbridge … Continued

October 2, 2020

A90 GLAMIS JUNCTION TO KIRRIEMUIR JUNCTION

£510,000 SURFACING IMPROVEMENTS   A90 Glamis Junction to Kirriemuir Junction, northbound   Works start Sunday 4 October for one week   A section of the A90 at Forfar is set to benefit from resurfacing improvements worth £510,000 with work set to get underway from Sunday. The improvements will address defects in the road surface on … Continued

September 23, 2020

A9 ALLAN WATER BRIDGE TO KEIR ROUNDABOUT

£320,000 WEEKEND RESURFACING IMPROVEMENTS    A9 Allan Water Bridge to Keir Roundabout, southbound    Works begin Thursday 24 September A section of the A9 southbound between Allan Water Bridge and Keir Roundabout is set to benefit from carriageway resurfacing improvements with work set to get underway later this week. The resurfacing improvements will take place … Continued

September 18, 2020

A90 SPURRYHILLOCK TO STONEHAVEN

£865,000 SURFACING IMPROVEMENTS   A90 Spurryhillock to Stonehaven, northbound   Works start Thursday 24 September for one week   A section of the A90 at Stonehaven is set to benefit from resurfacing improvements starting next week. The £865,000 improvements will address defects in the road surface on the northbound section of the A90 between the … Continued

September 14, 2020

A9 BALHALDIE TO GREENLOANING

NEW £170,000 ROAD SAFETY BARRIER IMPROVEMENTS PROJECT UNDERWAY ON A9 BALHALDIE TO GREENLOANING  Work to take up to two weeks   A road safety improvement project on the A9 near Dunblane worth £170,000 is underway this week. The project will see improvements to the central reservation safety barrier between Balhaldie and Greenloaning to help ensure … Continued

September 11, 2020

A92 NEWTONHILL TO CAMMACHMORE

£230,000 OVERNIGHT SURFACING IMPROVEMENTS   A92 Newtonhill to Cammachmore, northbound   Works start Monday 14 September for five nights   A section of the A92 at Newtonhill is set to benefit from resurfacing improvements worth £230,000 with work set to get underway next week. The improvements will address defects in the road surface on the … Continued