M876 OVERNIGHT MAINTENANCE

July 17, 2024

  • Overnight lane and carriageway closures 28 July to 10 August 2024

Overnight lane and carriageway closures will be in place on the M876 from the evening of 28 July to the morning of 10 August, to allow Transport Scotland’s operating company BEAR Scotland to carry out a variety of routine maintenance tasks.

Works to be carried out include gully cleaning, road sweeping, removal of vegetation and carriageway repairs.

Dates, locations and diversion routes for closures are listed in the table below.

Date Time Location Traffic mgt Diversion
28-30 July
(3 nights)
20:30-05:30 M876 northbound,
M80 Jct 8 to M876 Jct 1
Lane 1 closure N/A
30 July
(1 night)
20:30-05:30 M876 northbound,
Jct 1 on-slip
Closure Divert via M876 SB to Haggs and return
30 July
(1 night)
20:30-05:30 M876 northbound,
Jct 1 off-slip
Closure Divert via M876 North Broomage (Jct2) and return on SB main carriageway
31 July
(1 night)
20:30-05:30 M876 northbound,
Jct 2 North Broomage to M9 3-lane section
Closure Via A88 Bellsdyke Road – A905  Bowtrees
1-2 August
(2 nights)
20:30-05:30 M876 southbound,
M9 3-lane section to Jct 1 Denny on-slip
Closure M9 NB to Jct 9, M80 SB to Haggs
5-6 August
(2 nights)
20:30-05:30 M876 southbound,
Jct 1 Denny to M80 Jct 8
Closure A883 – A803 Bonnyfield Dennyloanhead – M80 Haggs
7 August
(1 night)
20:30-05:30 M876 southbound,
M9 Jct 7 off-slip
Closure M9 SB – M9 Jct 6 – M9 NB Jct 6 on-slip
7 August
(1 night)
20:30-05:30 M876 southbound,
Jct 7 on-slip
Closure M9 3 Lane Section – M876 SB to North Broomage – Return NB on M876 to M9 SB
8 August
(1 night)
20:30-05:30 M876 northbound,
Jct 7 off-slip to Bowtrees
Closure M9 3 Lane Section – M876 SB to North Broomage – Return NB on M876 to M9 SB
8 August
(1 night)
20:30-05:30 M876 northbound,
Jct 2 North Broomage off-slip
Closure M876 NB – M9 3 Lane Section – M876 Bowtrees – M9 Jct 7 NB on slip – 3 lane section – M876 SB – North Broomage off slip
9 August
(1 night)
20:30-05:30 M876 northbound,
Bowtrees off-slip
Closure A876 to Higgins Neuk Roundabout -SB to Bowtrees
9 August
(1 night)
20:30-05:30 M876 southbound,
Bowtrees on-slip
Closure A876 to Higgins Neuk Roundabout -SB to Bowtrees

 

Consultation has been carried out with emergency services and other relevant stakeholders to share information about the works in advance.

Tommy Deans, BEAR Scotland’s South East Network Manager, said: “It is essential for the safety of the workforce that we close the carriageway while these works are carried out, however we’ll be taking advantage of the closures to carry out as many routine maintenance tasks as possible, reducing the overall need for closures and traffic management.

“We’re grateful to road users and the local community for their patience and understanding.”

Real time journey information is available from Traffic Scotland at www.traffic.gov.scot, or on X at @trafficscotland.