Works to continue for three weeks

 

 

A footway refurbishment project on a section of the A92 southbound footway between Letham Junction and Fernie Castle Junction in Fife is underway this week.

The £20,000 project will involve teams resurfacing a 700m section of the southbound footway next to the A92, creating a safer route for pedestrians in the area to help promote active travel.

The project is scheduled to begin today, Monday 28 June, and will take place over three weeks with all work expected to be completed by Friday 16 July.  During this period the footway will not be available to pedestrians.

To ensure roadworkers and road users are kept safe during the project, a series of phased restrictions will be in place as follows:

 

  • Phase One – Monday 28 June to Friday 2 July (five days)

Temporary traffic lights will be in place Monday to Friday between 9.30am and 3.30pm each day.

 

  • Phase Two – Sunday 4 July to Thursday 8 July (five nights)

Temporary traffic lights will be in place overnight Sunday to Thursday between 7.30pm and 6.30am each night.

 

  • Phase Three – Sunday 11 July to Friday 16 July

Temporary traffic lights will be in place overnight Sunday to Thursday between 7.30pm and 6.30am, then during the daytime Monday to Friday between 9.30am and 3.30pm.

 

All traffic management will be removed outwith working hours.

Consultation has taken place with relevant stakeholders in advance of the footway refurbishment to make them aware of the traffic management arrangements.

 Ian Stewart, BEAR Scotland’s North East Representative, said: “This latest £20,000 investment from Transport Scotland will allow us to carry out footway refurbishment works on this section of the A92 between Letham Junction and Fernie Castle Junction to help improve the footway for all those who use it, and promote safer active travel links.

“The traffic management is essential to ensure the safety of roadworkers and motorists during this project. To help minimise delays as much as possible, we’ve planned the improvements to take place outside of peak times, and our teams will do all they can to complete the works as quickly and safely as possible.

“We thank motorists for their patience in advance while our teams carry out these footway improvements on the A92. We encourage road users to plan their journeys in advance by checking the Traffic Scotland website for up to date traffic information and allow some extra time to reach their destination.”

Real-time journey planning information can be obtained by visiting www.trafficscotland.org, twitter at @trafficscotland or the new mobile site my.trafficscotland.org