February 16, 2022

OVERNIGHT CLOSURES OF M9 AT HILL BRIDGE

Northbound carriageway closure Saturday 19 February 2022 Southbound carriageway closure Sunday 20 February 2022 Overnight carriageway closures will be in place on the M9 on Saturday 19 and Sunday 20 February, as part of the project to replace bearings and safety barriers on the bridge that carries the eastbound M876 over the M9 at Junction … Read Full Article

February 15, 2022

£400,000 OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR A96 PITCAPLE

Tuesday 15 February   OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR A96 PITCAPLE RESCHEDULED DUE TO FORECAST ADVERSE WEATHER   Please be advised that overnight surfacing improvements planned for a section of the A96 in Pitcaple, outlined in the release below, have been rescheduled. The project had been programmed to get underway from Sunday 13 February over … Read Full Article

February 14, 2022

RESURFACING THE M9 JUNCTION 10 SOUTHBOUND

WORKS POSTPONED: These works will be rescheduled during March, as a knock-on result of other works in the programme being extended due to adverse weather. Overnight carriageway closure Friday 18 February 2022 Motorists using the M9 southbound at Junction 10 Craigforth are set to benefit from an improved road surface, with resurfacing works planned for … Read Full Article

February 11, 2022

PEDESTRIAN CROSSING IMPROVEMENTS FOR A85 CRIEFF

Project set to begin on Monday 28 February for five weeks   Two pedestrian crossings on High Street in Crieff are to be upgraded to new signalised puffin crossing systems to improve road safety in the area, with works set to get underway from Monday 28 February. The five week project will involve teams installing … Read Full Article

February 11, 2022

RESURFACING THE A702 AT BOGHALL FARM

Overnight works on Wednesday 2 March 2022 Overnight works to renew the road surface on the A702 at Boghall Farm in Midlothian are planned for the night of Wednesday 2 March. Transport Scotland’s operating company BEAR Scotland will carry out the project, with all works to be completed between 19.30 and 06.30. For the safety … Read Full Article

February 10, 2022

A1 RESURFACING WORKS AT THISTLY CROSS

WORKS RESCHEDULED: Due to adverse weather, these works will now take place from Wednesday 2 to Friday 11 March from 19:30 to 06:00, with no works planned on Saturday or Sunday night (8 nights in total). Overnight northbound closures scheduled for 1-4 March The A1 is set to benefit from an improved road surface, with … Read Full Article

February 10, 2022

OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR A85 NEAR ARDCHYLE

Friday 18 February   OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR A85 NEAR ARDCHYLE RESCHEDULED DUE TO ADVERSE WEATHER   Please be advised that overnight surfacing improvements planned for a section of the A85 near Ardchyle have been rescheduled. The project had been programmed to get underway on, Tuesday 15 February for ten nights but has now … Read Full Article

February 10, 2022

RESURFACING THE A876 NORTH APPROACH JUNCTION, KINCARDINE

Overnight road closures Monday 21 and Tuesday 22 February 2022 Transport Scotland’s operating company BEAR Scotland is planning to resurface 100 metres of the A876 at the North Approach Junction in Kincardine on the nights of Monday 21 and Tuesday 22 February. To ensure the safety of the workforce and members of the travelling public, … Read Full Article

February 8, 2022

BEAR SCOTLAND WELCOMES A RECORD NUMBER OF NEW STUDENT PLACEMENTS FROM ABERTAY UNIVERSITY

In February, BEAR Scotland welcomed 13 new student placements from Abertay University as part of their BEng Civil Engineering degree. This is the largest intake the company has hosted to date. During the 12-week placement, the third-year civil and environmental engineering university students will be working with some of the teams in BEAR’s Perth office … Read Full Article

February 8, 2022

RESURFACING THE SOUTHBOUND M9 PRIOR TO AVON BRIDGE

Three overnight carriageway closures begin Tuesday 15 February 2022 A section of the southbound M9 is to benefit from a £200,000 Transport Scotland investment in resurfacing improvements, with operating company BEAR Scotland planning to renew approximately 0.7 kilometres of the trunk road. For the safety of workers and road users, the southbound carriageway of the … Read Full Article

February 8, 2022

NEW ROAD SAFETY AND FOOTWAY PROJECT UNDERWAY ON A83 IN MINARD

First phase of works to continue for three weeks   The first phase of a new £75,000 road safety project is underway on the A83 in Minard. The project will involve teams installing approximately 190 metres of new footway between the northern end of Minard and the access to Crarae Garden. Works will also include … Read Full Article

February 8, 2022

SAFETY AND STRUCTURAL INSPECTIONS AND INVESTIGATION WORK AT M80 JUNCTION 4A LOW WOOD

Work to take place overnight from Monday 14 February for nine nights Overnight carriageway closures required for safety, 8pm to 6am Ongoing lane closures on A8011 Glasgow Road remain in place for safety to reduce vehicle loading while inspections continue     Essential structural inspection and investigation works are continuing on the M80 at Junction … Read Full Article