OVERNIGHT WORKS ON A1

May 14, 2024

Highway maintenance vehicle
  • Four weeks of work from Old Craighall to Thistly Cross roundabout 27 May 2024

  • Work to be completed in phases

Transport Scotland’s operating company, BEAR Scotland, will undertake a four-week programme of overnight maintenance on the A1 from Old Craighall to Thistly Cross roundabout.

Works to be carried out during these closures include litter picking, grass cutting, gully emptying, catchpit cleaning, weed spraying, road sweeping, pothole patching, inspection of structures and repairs to signs.

The work will be carried out in phases, with overnight closures on different sections of the bypass in each phase. Overnight closures will be in place on the dates and locations listed below, from 19:30 until 05:30 each night. Diversion routes will be signposted where indicated:

Start End Location Duration Traffic mgt Diversion route (if applicable)
27-May 29-May Old Craighall to Wallyford 2 nights Total closure Old Craighall-A720 Millerhill- Jct-A68 Salters Jct-A6094-Wallyford on slip
29-May 30-May Wallyford to Dolphingstone 1 night Total closure Wallyford-A6094-A199 Dolphingstone on slip
30-May 01-Jun Dolphingstone to Gladsmuir Part 1 2 nights Total closure Dolphingstone A199-Gladsmuir on slip
02-Jun 03-Jun Dolphingstone to Gladsmuir Part 2 1 night Total closure Dolphingstone A199-Gladsmuir on slip
03-Jun 05-Jun Gladsmuir to Abbotsview 2 nights Total closure Gladsmuir A199-Abbotsview on slip
05-Jun 08-Jun Abbotsview to Thistly Cross Roundabout 2 nights Total closure Abbotsview -A199 -Thistly Cross Roundabout
10-Jun 13-Jun Thistly Cross Roundabout to Abbotsview 3 nights Total closure Thistly Cross Roundabout-A199-Abbotsview on slip
13-Jun 15-Jun Abbotsview to Gladsmuir 2 nights Total closure Abbotsview-A199-Gladsmuir
16-Jun 17-Jun Gladsmuir to Dolphingstone 1 night Total closure Gladsmuir-A199-Tranent- A199 Dolphingstone on slip
17-Jun 20-Jun Gladsmuir to Wallyford 3 nights Total closure Gladsmuir-A199- Tranent – Dolphingstone -A6094-Wallyford on slip
20-Jun 22-Jun Dolphingstone to Old Craighall 2 nights Total closure Dolphingstone- A199-A6094-Wallyford -Whitecraig –Salters Jct- A68- Millerhill Jct-A720-Old Craighall Roundabout

 

Consultation has been carried out with emergency services and other relevant stakeholders to share information about the project in advance.

Tommy Deans, BEAR Scotland’s South East Network Manager, said: “It is essential for safety that we close the carriageway while these works are carried out, however we’ll be taking advantage of the closures to carry out as many routine maintenance tasks as possible at once.

“We’ve also split the works into phases so that only the minimum length of carriageway has to be closed on any given night.

“If you are planning to use the A1 at night over the next few weeks, our advice is to check what restrictions will be in place and allow extra time for your journey if necessary.

“We thank road users and the local community for their patience and understanding.”

Real time journey information is available from Traffic Scotland on www.trafficscotland.org, twitter at @trafficscotland or the new mobile site my.trafficscotland.org.