REVISED DATES FOR ESSENTIAL UNDER-DECK MAINTENANCE ON QUEENSFERRY CROSSING

November 15, 2024

  • Temporary lane realignment and speed restriction on northbound carriageway now planned for up to 16 days, 1 to 17 December 2024

Forth Crossing Bridge Constructors (FCBC) has advised of an amended programme for essential underdeck maintenance at the south end of the Queensferry Crossing, with further time being taken to safely plan the works ahead of implementation.

The works, which are being undertaken on behalf of Transport Scotland, will now require traffic management to be installed on the M90 northbound carriageway on the night of Sunday 1 December. (8pm to 6am).  The traffic management will consist of a temporary realignment of the running lanes using traffic cones, necessitating closure of a short length of the hard shoulder.

Two lanes will be maintained at all times and the traffic management will be removed on 17 December subject to weather not delaying the works.

A 50mph temporary speed limit will be applied to the northbound carriageway and a free vehicle recovery service will be provided to attend to any breakdowns within the roadworks area.

Northbound abnormal loads will be required to divert via Clackmannanshire Bridge whilst traffic management is in place.

The southbound carriageway is not affected by the works.

Motorists using the Queensferry Crossing are encouraged to plan ahead during the works by checking the Traffic Scotland website www.traffic.gov.scot for up-to-date travel information.

BEAR Scotland is supporting this project as part of its responsibility for the South East Trunk Road Network on behalf of Transport Scotland. FCBC and its subcontracted supply chain will be undertaking the work on site.