£35,000 ROAD SAFETY IMPROVEMENT PROJECT PLANNED FOR A83 EAST OF INVERARAY

March 18, 2022

Project set to begin on Monday 21 March for five days   A new road safety project on the A83 between Inverary and Garron Bridge is set to get underway from Monday 21 March. The £35,000 investment from Transport Scotland will see teams installing 160 metres of safety barrier adjacent to the A83 to facilitate … Continued

£350,000 OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR THE A83 SOUTH OF ARROCHAR

March 15, 2022

Friday 1 April TWO ADDITIONAL OVERNIGHT CLOSURES REQUIRED TO COMPLETE SURFACING IMPROVEMENTS ON THE A83 SOUTH OF ARROCHAR   Please be advised that inclement weather has impacted the ongoing resurfacing works on the A83 south of Arrochar. The project was due to be completed by Friday 1 April, however additional road closures will be required … Continued

A83 REST AND BE THANKFUL

February 23, 2022

Thursday 24 February – 9.20am   A83 AT REST AND BE THANKFUL TO CONTINUE TO OPERATE UNDER CONVOY CONTROL ON THE A83 TODAY (THURSDAY) AND OVERNIGHT DUE TO FORECAST HEAVY SNOW     Given the heavy snow forecast today, convoy control operations on the A83 will continue through today and overnight.  Journey times through the … Continued

NEW ROAD SAFETY AND FOOTWAY PROJECT UNDERWAY ON A83 IN MINARD

February 8, 2022

First phase of works to continue for three weeks   The first phase of a new £75,000 road safety project is underway on the A83 in Minard. The project will involve teams installing approximately 190 metres of new footway between the northern end of Minard and the access to Crarae Garden. Works will also include … Continued

£200,000 OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR A83 BALURE TO TAYINLOAN

December 3, 2021

Friday 3 December   ADDITIONAL OVERNIGHT ROAD CLOSURE REQUIRED TO COMPLETE SURFACING IMPROVEMENTS ON THE A83 BETWEEN BALURE AND TAYINLOAN FROM 8PM SUNDAY 5 DECEMBER   Please be advised that an additional overnight closure to complete surfacing improvements on the A83 between Balure and Tayinloan will take place on Sunday 5 December. The project was … Continued

£220,000 SURFACING IMPROVEMENTS PLANNED FOR A83 NEAR LOCHGILPHEAD

September 17, 2021

Friday 17 September   ONGOING SURFACING IMPROVEMENTS ON A83 EAST OF LOCHGILPHEAD TO SWITCH TO OVERNIGHT WORKING   Please be advised that ongoing surfacing improvements on the A83 east of Lochgilphead are set switch to overnight working to ensure the project is completed safely. The project got underway this week with teams carrying out improvements … Continued

ESSENTIAL OVERNIGHT ROAD MAINTENANCE PLANNED FOR THE A83 AT MINARD  

September 10, 2021

 Works start on Tuesday 14 September for four nights Overnight road closures in place for safety, between 7pm and 2am An essential road maintenance project on the A83 between Inverary and Lochgilphead is set to get underway next week. The overnight project will involve teams reinstating traffic loops across a section of the A83 near … Continued

THE NEXT PHASE OF LANDSLIP MITIGATION MEASURES AT A83 REST AND BE THANKFUL UNDERWAY

September 7, 2021

Next stage expected to take approximately nine months to complete The next stage of landslip mitigation measures at the Rest and Be Thankful got underway this week to help improve landslip resilience to the A83. The £3.5M project will see the construction of a further catch-pit next to the trunk road, and will be located … Continued

NEW £300,000 SURFACING IMPROVEMENT PROJECT PLANNED FOR FOUR LOCATIONS ON THE A830 BETWEEN BEASDALE AND CORPACH

August 13, 2021

Project begins Wednesday 18 August for up to three weeks   Four sections of the A830 between Beasdale and Corpach are set to benefit from an improved road surface as a £300,000 surfacing project gets underway next week. The project will see four sections of the A830 resurfaced, including two sections in proximity to Polnish, … Continued

£470,000 SURFACING IMPROVEMENTS PLANNED FOR A83 CAMPBELTOWN

August 2, 2021

Project set to begin from Tuesday 3 August for three weeks Three sections of the A83 in Campbeltown are set to benefit from an improved road surface with work set to get underway this week. The project will see over 1km of the A83 through Campbeltown resurfaced, creating a safer and smoother journey for road … Continued

A835 BRAEMORE HALL TO LETTERS JUNCTION

July 6, 2021

£245,000 SURFACING IMPROVEMENTS Works start on Wednesday 7 July for seven days     Motorists using the A835 between Braemore Hall and Letters Junction are to benefit from an improved road surface as £245,000 worth of resurfacing works are set to get underway tomorrow. The project will see almost two kilometres of carriageway resurfaced north … Continued

£350,000 OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR A83 MINARD

June 29, 2021

Project to begin from Sunday 4 July for two weeks Overnight road closures in place for safety, 8pm and 5am   A section of the A83 between Inveraray and Lochgilphead is set to benefit from an improved road surface with work set to get underway on Sunday. The project will see over one kilometre of … Continued