The third quarter of 2024 promises to be a busy time for maintenance and improvement on the trunk road network, with a number of major schemes in progress or due to commence.
A total of 25 resurfacing schemes are planned on routes across the network. Some of the most significant include on the A720 from Lothianburn to Straiton, the A702 south of Coulter and the M8 westbound at Harthill.
Road closures will be required to carry out these works, but they will be scheduled at night wherever possible to minimise disruption. The scheme on the M8 westbound at Harthill is likely to require some weekend restrictions – details will be confirmed in due course.
A full list including provisional start dates is set out below:
Start date | Scheme name |
08-Jul | A702 Dolphinton |
15-Jul | M8 Prior to Junction 3 WB |
22-Jul | A702 Easter Howgate |
24-Jul | A702 Damhead to Hillend |
29-Jul | M8 Junction 5 WB On Slip |
02-Aug | A702 Lothianburn North Roundabout |
05-Aug | A720 Lothianburn to Straiton EB Ph 5 |
10-Aug | M9 Junction 7 Northbound Offslip |
14-Aug | M9 Between Junction 7 NB Slips |
19-Aug | M9 After Junction 10 NB |
20-Aug | M8 Junction 4 WB Off Slip |
21-Aug | A702 Overburns to Coulter |
26-Aug | M8 Hermiston EB Off Slip |
29-Aug | M8 Prior to Junction 3a EB |
02-Sep | M8 Prior to Junction 4 EB |
05-Sep | A702 Coulter |
07-Sep | M8 Harthill WB |
07-Sep | M8 Harthill WB Off Slip |
09-Sep | A68 Oxton to Climbing Lane |
16-Sep | A68 Soutra to Gilsdean |
18-Sep | A68 Pathhead |
20-Sep | M8 Harthill Services WB Bus Stop |
23-Sep | M8 Harthill WB On Slip |
24-Sep | A876 WB Off-Slip to Bowtrees |
25-Sep | A977 Gartrarry Roundabout |
Major works are due to commence in September at Longacre Bridge east of M8 Junction 6, requiring some weekend restrictions, and on the bridge that carries the B792 over the M8 at Blackburn, requiring a number of overnight closures.
The ongoing projects to refurbish Westwater Bridge on the A702 and the bridge carrying the M8 Junction 3 eastbound off-slip over the A899 are also set to continue until later in the year.
Work to replace the architectural lighting on the Queensferry Crossing will continue throughout the quarter, as will the project to replace the Kincardine Bridge’s Southern Piled Viaduct and several maintenance projects on the Forth Road Bridge, however these are not expected to cause any significant disruption to road users.
Finally, a number of lower impact routine maintenance schemes are planned:
Scheme | Description | TM | Timescale | When |
M9 Newline to Chartershall NB | Drainage investigation | Night-time lane closures | 4 weeks | September |
A720 Lothianburn to Baberton WB | Filter stone replacement and widening drain width. Pipe repairs. Ditch cleaning. Upscaling pipework. Further jetting & investigation | Night-time lane closures and junction on and off slip closures | 10 weeks | August to October |
A876 Bowtrees to Kilbagie | Drainage investigation | Night-time lane closures and junction on and off slip closures | 5 weeks | July |
M80 River carron to Bannockburn NB | Filter stone replacement and widening drain width. Pipe repairs. Ditch cleaning. Upscaling pipework. Further jetting & investigation. Gully cover replacement | Night-time lane closures | 10 weeks | Ongoing in July, then resrting in mid September |
M8 Polkemmet EB | Pipe repairs & replacement | Night-time lane closures | 2 weeks | July |
M9 Prior to junction 4 | Filter stone replacement and widening drain width. Pipe repairs. | Night-time lane closures | 2 weeks | July |
M9 NB junction 2 to 3 | Boundary fence replacement | Hard shoulder closure | 6 weeks | Sept to Nov |
M9 SB junction 5 to Avondale | Boundary fence replacement | Hard shoulder closure | 6 weeks | Sept to Nov |
M9 Keir RbT to Scotbeef SB Junction 11 to 10 | Boundary fence replacement | Hard shoulder closure | 4 weeks | Nov to Dec |