South East trunk roads – Lookahead to Q4 2024

October 24, 2024

A total of 26 resurfacing schemes are planned on trunk roads across South East Scotland in the final quarter of 2024, continuing Transport Scotland’s ambitious programme of investment in the trunk road network. 

Road closures will be required to carry out these works safely, however they will be scheduled at night wherever possible to minimise disruption. 

A full list including provisional dates is set out below: 

Route  Scheme name  Provisional start date  Provisional end date 
A1  Heugh Head  21/10/2024  15/11/2024 
A1  N of Greystonlees Jct to Burnmouth  18/11/2024  18/11/2024 
A68  South of Carfraemill  19/11/2024  27/11/2024 
A68  Wiselawmill  28/11/2024  28/11/2024 
A68  Ravenswood to River Tweed   02/12/2024  04/12/2024 
A7  Kingsknowe RBT   05/12/2024  06/12/2024 
A1  Spott RBT   09/12/2024  10/12/2024 
A1  Thistly Cross RBT  11/12/2024  12/12/2024 
A1  North Oaktree SB  13/12/2024  18/12/2024 
M90  Junction 2 SB  14/10/2024  16/10/2024 
M90  Junction 2 Southbound Offslip   17/10/2024  17/10/2024 
M90  Junction 2 Northbound  21/10/2024  23/10/2024 
M90  Junction 3 NB  24/10/2024  25/10/2024 
A985  Crombie   28/10/2024  01/11/2024 
A985  High Valleyfield  04/11/2024  12/11/2024 
M9  Junction 9 SB Offslip  13/11/2024  15/11/2024 
M9  Torwood SB  18/11/2024  20/11/2024 
M9  Between J5 to J4 Hard Shoulder SB  21/11/2024  22/11/2024 
M80  Stoneywood to Easterton NB  21/11/2024  29/11/2024 
A985  Rosyth  02/12/2024  12/12/2024 
M80  North of Haggs NB   09/12/2024  11/12/2024 
A702  Abington South Roundabout  10/12/2024  12/12/2024 
A702  Robinsland Roundabout  16/12/2024  16/12/2024 
M876  Junction 1 EB Offslip  17/12/2024  17/12/2024 
M876  Junction 1 EB On Slip  18/12/2024  18/12/2024 
M876  After Junction 1 EB On Slip  19/12/2024  19/12/2024 

 

On the South East unit’s bridges, major works at Longacre Bridge east of M8 Junction 6 are due to conclude in October, requiring weekend restrictions. Strengthening works on the bridge carrying the M90 southbound over the B9080 at Kirkliston are expected to be complete by the end of December, and the ongoing project to refurbish Westwater Bridge on the A702 will to continue until later in the year. 

The project to replace the Kincardine Bridge’s Southern Piled Viaduct is set to take a major step forward in November, with the new viaduct due to open to traffic for the first time. 

Work to replace the architectural lighting on the Queensferry Crossing will continue into November. 

Several maintenance projects are under way on the Forth Road Bridge, however these are not expected to cause any significant disruption to road users.